Ballast replacement, Hengselva bridge
Start: January 2025
Completion: June 2025
Project Description
Railvac carried out ballast replacement on the Hengselva bridge for Bane NOR.
Using a Railvac and MVS ballast wagons with conveyor belts, Baneservice replaced the ballast and lowered 270 metres of track. Around 800 tonnes of material was replaced. In addition, Baneservice replaced sleepers and installed guard rails at both ends. The track tamping department carried out tamping after the ballast replacement.
Client: Bane NOR