Ballast replacement, Hengselva bridge
Morten Munthe

Ballast replacement, Hengselva bridge

Location:
Meheia, Norway
Railvac carried out ballast replacement on the Hengselva bridge for Bane NOR.

Start: 6 January 2025
End: 20 June 2025

Using a Railvac and MVS ballast wagons with conveyor belts, Baneservice replaced the ballast and lowered 270 metres of track. Around 800 tonnes of material was replaced. In addition, Baneservice replaced sleepers and installed guard rails at both ends. The track tamping department carried out tamping after the ballast replacement.

Kontaktperson:

No items found.

Oppdragsgiver:

Keywords:
Baneservice

Prosjekt start/slutt:

Start:
Slutt:

Kontraktsum

Entrepriseform:

Aktuelt fra Baneservice

7.5.26

Measuring almost 50 metres, this is Scandinavia's first hybrid tamping machine

Les mer
5.6.26

Hove train stabling project certified BREEAM Infrastructure Excellent

Les mer
16.2.26

Baneservice strengthens its position through acquisitions in the Nordics

Les mer
Se alle nyheter